Update GMP clean room area, laboratory area and upcoming construction completion (1/4)

by Cannerald
Posted on November 11, 2022 13:00

Dear Cannerald and CannerGrow Community,


in this four-part blog series you will receive all important updates about CannerGrow and Cannerald. In addition to the blog article, each part also includes a video statement from our CEO Levin Amweg.
It may be that the videos contain form errors due to the length and many details. Therefore, in addition to the videos, we ask you to read the corresponding blog article if you have any questions.

Structure of the blog series and videos:
1. New tour: insight into the upcoming GMP area in Fraubrunnen, update on the construction progress of the biology and biochemistry laboratory, update on the construction progress of Yankee and Zulu
2. Detailed explanation of the increase in service costs
3.1 What does this mean for Cannerald?
3.2 Forecast into the future
4. Current upcoming questions

In the first video you accompany our CEO Levin Amweg through our production facility in Fraubrunnen. Together you will look at the clean room area, the laboratory area and the current construction progress in the grow rooms Yankee and Zulu.


Over the next few months we will be providing you with more and more information about cannabis, genetics and our production to give you an even more detailed insight into our company.
There will be a large FAQ article on the subject of CannerGrow in the next few weeks with many updates, which should then answer almost all of your questions.

Furthermore, in this blog article we have pictures of the completion of the construction of the grow rooms Sierra, Tango, Uniform, Victor, Whiskey and X-ray for you.
The completion of the construction of the grow rooms Kilo, Lima, Mike, November, Oscar, Papa, Quebec and Romeo has already taken place in the
last construction progress video here (click).

Completion grow room Sierra:
Picture following in the next 48 hours


Completion grow room Tango:


Completion grow room Uniform:


Completion grow room Victor:


Completion grow room Whiskey:


Completion grow room X-ray:


Current construction progress room Yankee:


Current construction progress room Zulu:



Tomorrow we'll continue with Part 2 of the four-part blog series, in which you'll get a detailed explanation from Levin about the recent increase in utility costs.


#WeGrowForYou
Your Cannerald & CannerGrow team