Construction Progress and Update of the final Start dates of the Grow Rooms

by Cannerald
Posted on August 21, 2022 13:00

Dear Cannerald and CannerGrow Community,

in this blog article we want to show you an update on the current status of the construction progress and give you an update on the final start dates of the grow rooms in Fraubrunnen.

First of all, please watch the video we recorded on Friday, August 19th, 2022:


Update of the final start dates for the grow rooms Kilo to Zulu, which will start every seven days from October 24, 2022:
Grow Room Kilo: 24.10.2022
Grow Room Lima: 31.10.2022
Grow Room Mike: 07.11.2022
Grow Room November: 14.11.2022
Grow Room Oscar: 21.11.2022
Grow Room Papa: 28.11.2022
Grow Room Quebec: 5.12.2022
Grow Room Romeo: 12.12.2022
Grow Room Sierra: 19.12.2022
Grow Room Tango: 26.12.2022
Grow Room Uniform: 02.01.2023
Grow Room Victor: 09.01.2023
Grow Room Whiskey: 16.01.2023
Grow Room X-ray: 23.01.2023
Grow Room Yankee: 30.01.2023
Grow Room Zulu: 06.02.2023

You can find a reason why the start dates of the grow rooms from Kilo to Zulu had to be updated in the YouTube video by co-founder Levin Amweg.


Update 26.09.2022:
As previously promised, here is an update on the start dates of the grow rooms in Solothurn:
The grow rooms in Solothurn will directly start after the grow rooms in Fraubrunnen. Here also in a seven-day cycle.
Grow Room Demeter: 13.02.2023
Grow Room Apollon: 20.02.2023
Grow Room Hera: 27.02.2023
Grow Room Athene: 06.03.2023
Grow Room Poseidon: 13.03.2023
Grow Room Hestia: End Q2/Beginning Q3 2023
Grow Room Zeus: End Q2/Beginning Q3 2023